This project included the installation of 550 MW Combined Cycle Power Plant featuring two General Electric 7FA Combustion Turbines, two ABB Heat Recovery Steam Generators, a single General Electric D-11 Steam Turbine Generator, Step-up Transformer, The scope of work includes the construction of the civil, mechanical piping, electrical and instrumentation portions of the project The project was performed over two severe winters in Northern Maine. The project consisted of pouring 10,000 yds of concrete in the winter.